Work delivered after several years and phases. One of our largest projects, as well as the most cutting-edge in the region:

  • 25 hybrid production units (operating with electricity and natural gas).

  • 15 UTAS.

  • 377 indoor air conditioning units.

  • More than 15,000 meters of fiber ducts.

  • More than 7,000 meters of refrigeration lines.

  • Diffusers: More than 600 supply grilles, 700 extraction grilles, 570 rotational diffusers, 234 linear diffusers and more than 100 fire and regulation dampers.

A work with great technical, personnel and logistical requirements and challenges. Completion and start-up where the value of a job well done by each person who has participated is verified. An achievement and a source of pride to finish everything we started.

 

SCI Group

Installation and Maintenance of Air Conditioning

  • LinkedIn
  • Facebook
  • Instagram

Legal warning

Privacy Policy

©2024 por Servicio y Calidad de Instalaciones S.L.

Cookie Policy

logo de nuestra empresa
bottom of page